Vision Zero injury and fatality data are generally tracking
with 2023 data.
B. Parks & Recreation Report
Ms. Godon reported progress on the Perche Creek Trail, including
1.5 miles of paved trail from the MKT to the Gillespie Bridge. She
also invited commission members to attend the last unveiling in an
annual series of community trail art posters. The event will be at
Walt’s Bike Shop on December 3, 2024
C. Planning Staff Report
Tim Teddy reported that the Commission’s recent correspondence
about future improvements to I-70 had been delivered to the City
Council in a report at the November 18, 2024 meeting.
D. Commissioner IP Meeting Reports
Chair Boyd asked City Staff try to assure that the
Commission is notified of upcoming IP meetings.
1. NE Columbia Sidewalk Projects, PM, We 12/11, 17:30-18:30, Oakland MS
Oakland Gravel Road (Blue Ridge Road to Smiley Lane):
2. East Walnut Traffic Calming PH, 12/2
3. Central Area Zoning and Design Guidelines
E. Commission Correspondence
No new correspondence.
1. Improve I70 Ph2 letter to Council as Report on 11/18
VI. NEW BUSINESS
A. Ash Street Sidewalks and Tree Removal
A. Allison Anderson from Public Works led a discussion and
answered questions about City plans to build sidewalks along
the north side of West Ash Street, between First Street and
Clinkscales. The current plans would take land and some trees
from the front yards of residents on Ash Street.