Columbia MO Return to CoMo.gov
File #: PH31-24    Version: 1
Type: Public Hearing Item Status: Approved
File created: 8/20/2024 Meeting Body: City Council
On agenda: 9/3/2024 Final action: 9/3/2024
Enactment date: Enactment #:
Title: Proposed addition of one (1) new 69 kV bus at the Bolstad Substation to provide for generation interconnection to the Boone Stephens solar facility.
Indexes: Capital Improvements, Public Hearing, Public Improvement Project, Utilities, Water & Electric
Attachments: 1. Council Memo, 2. Location Map
Related files: B337-19, B325-21, B407-21, B74-24, R140-24, B228-24
Department: City Utilities

Title

Proposed addition of one (1) new 69 kV bus at the Bolstad Substation to provide for generation interconnection to the Boone Stephens solar facility.

Recommended Action

[Need Motion/Mayor]